Diablo Vista Middle School Special Education Restroom

Diablo Vista Middle School Special Education Restroom

This project consists of converting a storage building on campus into a Special Day bathroom that includes a shower, changing table, and lift system. The project also consists of adding one single-occupancy restroom on campus.

Timeline and Updates

Fall 2017

The plumbing contractor is working after hours to complete the rough-in. The other contractors will wrap up any remaining work in the walls and then start placing finishes. Do to the constraints of working on a live campus next to a Special Day Classroom with students that are adversely affected by noises and smells, all work is being done after hours. Construction is approximately 70% complete and is anticipated to be substantially complete in 3-4 weeks.

Summer 2017

Installation of plumbing, electric, HVAC, and framing scheduled to begin in fall 2017.

SRVUSD Celebrates with Groundbreaking Ceremony for San Ramon Valley High School Project

A historic groundbreaking ceremony took place on Wednesday, May 17, 2017, at San Ramon Valley High School (SRVHS) in celebration of the beginning of the largest project funded by the $260 million Measure D Facilities bond. The event was attended by SRVUSD Board Members and Superintendent, Mayor of the Town of Danville,  Contra Costa Supervisor… Continue Reading

SRVHS Construction Update

The SRVUSD Board of Education approved the second set of bid packages for the SRVHS Building Project at their meeting on May 2, 2017. Contractors are mobilizing their equipment and underground utility excavation will begin this week, while the building footing excavation will begin later in May. We continue to coordinate construction activities with the… Continue Reading

Stone Valley Middle School Construction Update

Construction at Stone Valley Middle School is moving along nicely following the heavy rains of the past months. Highlights of what is taking place this April include: Classroom building: we are pouring the building footings this week and next. Underground plumbing is complete and the underground electrical is underway. Multi-Purpose Room building: we will begin… Continue Reading

San Ramon Valley High School Project Moves Forward

At their December 6, 2017, Board Meeting, the San Ramon Valley Unified School District (SRVUSD) Board of Education Trustees unanimously approved the 90 percent drawings and updated cost estimate for San Ramon Valley High School’s new 52 classroom, 3-story, academic building. The project will dramatically improve campus functionality, pedestrian flow, campus supervision and safety, and the… Continue Reading

Public construction terminology can be challenging to navigate. Fortunately the California School Boards Association has the following great resource:

Glossary of Construction Management Terms

The San Ramon Valley Unified School District stands among the highest-achieving school districts in California. It covers 18 square miles, encompassing the communities of Alamo, Blackhawk, Danville, Diablo, and San Ramon (including the new Dougherty Valley communities in east San Ramon) as well as a small portion of Walnut Creek.